Wednesday 16 May 2012

140kWp Case Study: Completion of a 140kWp poultry farm is an eggcellent result!




CTS Renewables are pleased to announce the completion of a 140kWp Solar Photovoltaic system to a poultry farm in Lincolnshire. The installation, which was an addition to a 50kWp system already in place, saw more than 580 panels and 8 inverters installed in just 10 days.

Paul West, Solar Project Manager for CTS Renewables said: “even though the size of the system was considerable we managed to get it completed, commissioned and witness tested in just 10 days. The client was keen to register the installation before the April 1st, the design and install process was efficiently managed, and the whole team pulled together to meet the deadline.”

Due to the high electricity consumption on the farm, each shed has its own electricity meter enabling the system to be designed and commissioned as three sub 50kWp systems, therefore attracting the higher Feed in Tariff rate. The system is estimated to cut the farm’s fuel bills by up to 30 percent, enabling the farm to achieve a significant savings as a result of the PV installation. CTS Renewables estimate that the payback period will be just 5 and a half years.

The installation was completed using 240w Jinko Solar polycrystalline solar modules and the Siemens PVM range of G59 three phase inverters. The solar pv system is expected to produce over 126,000kWh of electricity per year.

Start date: 16/03/12
Completion date: 26/03/12
Modules: Jinko Solar 240W Poly
Inverter: Siemens PVM17 and Siemens PVM20
Mounting system: Schuco
Power Specification (kW, MW): 140kW
Annual Power Output (kW, MW): 126,081
Annual carbon dioxide saving: Over 60 Tonnes
Expected ROI: 5.5 Years.